Mechanics Liens on a California Custom Home: Lien Releases, Deadlines and Retention

Last updated: November 2026
Short answer: On a California custom home, anyone who supplies labor or materials can record a mechanics lien against your property if they are not paid, even if you paid your general contractor. You protect yourself by collecting California's statutory lien releases with every payment, tracking preliminary notices from subcontractors and suppliers, and recording a notice of completion when the house is finished. That notice shortens the lien recording window from 90 days to 60 days for the direct contractor and 30 days for everyone else.
Most owners never see a lien, but on a multi-million-dollar build with dozens of trades, the paperwork is what keeps it that way. This guide explains the forms, the deadlines and the payment habits that keep title clean through construction.
What is a mechanics lien on a custom home?
A mechanics lien is a claim against the property, not just against the person who hired the work. If a subcontractor or supplier is not paid, it can record a lien and ultimately sue to foreclose on it. The Contractors State License Board warns owners that paying their contractor, or getting a release from the contractor, does not guarantee that other claimants such as subcontractors and suppliers are paid. [Source: CSLB]
That is the core risk on a custom home. The owner pays the general contractor in good faith, the general contractor fails to pay a framer or a window supplier, and the lien lands on the owner's title. Lenders know this, which is why construction loans release funds against signed lien releases, as our guide to construction loans for custom homes explains.
What are the California lien release forms?
California requires lien releases to substantially follow one of four statutory forms in Civil Code sections 8132, 8134, 8136 and 8138. [Source: CSLB] A release in any other format may not protect you.
| Form | Civil Code | When to collect it |
|---|---|---|
| Conditional waiver and release upon progress payment | 8132 | Before you pay a progress payment |
| Unconditional waiver and release upon progress payment | 8134 | After the payment has cleared |
| Conditional waiver and release upon final payment | 8136 | Before the final payment |
| Unconditional waiver and release upon final payment | 8138 | After the final payment has cleared |
Source: CSLB, Conditional and Unconditional Waiver and Release Forms.
The conditional progress release is effective only if the claimant is actually paid, and no release is binding unless the claimant signs and delivers it. In practice, owners collect a conditional release with each payment request and the matching unconditional release with the next one, proving the previous payment arrived.
What are the mechanics lien deadlines in California?
Three deadlines matter most. A preliminary notice should be served within 20 days after a party first furnishes labor or materials. A lien generally must be recorded within 90 days after completion of the project, shortened to 60 days for direct contractors and 30 days for subcontractors and suppliers when a notice of completion is properly recorded and served. A lien claimant must then file suit to foreclose within 90 days after recording. [Source: Allen Matkins]
| Step | Deadline |
|---|---|
| Preliminary notice | Within 20 days of first furnishing work |
| Record lien, no notice of completion | 90 days after completion |
| Record lien, notice of completion recorded | 60 days (direct contractor), 30 days (others) |
| Sue to foreclose | 90 days after recording the lien |
Source: Allen Matkins, Understanding and Addressing Mechanics Liens on California Projects.
Preliminary notices are your map of who could lien. Keep every one you receive, and make sure each trade that sent one appears on the releases before final payment.
How much retention can be held on a custom home?
Retention, the portion of each payment held back until completion, is set by your contract on a single-family custom home. California's SB 61 caps retention at 5 percent on private works contracts entered into on or after January 1, 2026, but it expressly does not apply to residential projects that are not mixed-use and do not exceed four stories. [Source: SB 61, Statutes of 2025]
So the retention percentage, and the conditions for releasing it, belong in the construction contract. Tie the final release of retention to the final inspection, a recorded notice of completion, and unconditional final releases from the contractor and every trade that served a preliminary notice.
How do you protect your property during construction?
Build lien protection into the payment routine. Before each payment, collect a conditional progress release from the general contractor and from major subcontractors and suppliers. With the next payment, collect unconditional releases for the previous one. Pay by check or wire so payment is documented, and compare the trades on the releases with the preliminary notices you have received. Documented payment matters at the end too: the conditional final-payment release is binding only on evidence of payment, such as a check endorsed by the claimant. [Source: CSLB]
When the house is finished, record a notice of completion to shorten the lien window. Large projects benefit from an owner's representative who reviews pay applications and releases line by line. Our guide to spotting a builder you can't trust covers payment red flags to watch for.
How Craftsmen's Guild handles payments and releases
Craftsmen's Guild is a family-owned design-build firm founded in 1988, with architects, designers and builders on one team. On a design-build project, the team that schedules the trades is also the team that collects their releases, so pay applications, preliminary notices and statutory release forms can be reconciled in one place for the owner and the construction lender. Ask us to walk you through that paperwork at your first meeting.
We build across the Peninsula and South Bay. See our custom home construction process, our overview of custom home builders in the Bay Area, and our custom home timeline guide. For budgeting, start with our 2026 cost guide.
Frequently asked questions
Can a subcontractor put a lien on my house if I paid my contractor?
Yes. A mechanics lien attaches to the property, so an unpaid subcontractor or supplier can record one even if you paid the general contractor in full. The Contractors State License Board warns that paying your contractor does not guarantee others are paid, which is why collecting releases from major trades matters.
What is the difference between a conditional and unconditional lien release?
A conditional release takes effect only when the claimant is actually paid, so it is safe to collect before payment. An unconditional release states that payment has already been received and is effective immediately, so collect it only after the payment clears.
How long does a contractor have to file a mechanics lien in California?
Generally 90 days after completion of the project. If the owner records and serves a notice of completion, the window drops to 60 days for direct contractors and 30 days for subcontractors and suppliers. A claimant then has 90 days after recording to file suit to foreclose.
Does the new 5 percent retention cap apply to my custom home?
No. SB 61's 5 percent cap applies to private works contracts entered into on or after January 1, 2026, but it excludes residential projects that are not mixed-use and are four stories or fewer. Retention on a single-family custom home is set by your contract.
This article is general information, not legal advice. For questions about a specific lien or contract, consult a California construction attorney.
Keeping title clean through construction
Mechanics liens are avoidable with routine: statutory releases with every payment, preliminary notices tracked against those releases, retention tied to completion, and a recorded notice of completion at the end. Owners who set this up before the first draw rarely think about liens again. When you are ready to plan your build, book a complimentary consultation with our team.
What We Build
- Custom Home ConstructionGround-up homes across the Peninsula and South Bay
- Home Remodeling & RenovationsWhole-house remodels, kitchens and baths
- ADUs: Accessory Dwelling UnitsDetached and attached secondary units
- Owner's RepresentativeWe manage the build on your behalf
Where We Build
All service areas
Ready to turn your vision into a stunning living space?
Schedule a complimentary consultation. We’ll listen, walk your space, and map a path forward.